New Jersey Natural Gas (NJNG) has released a two-week plan to re-gas sections of the Barrier Island from Mantoloking to South Seaside Park beginning Monday, December 3. The plan is to divide the system into seven sections with crews following behind to rebuild meter sets until all customers who can be serviced again have been. The seven sections have been split as follows:

Pressurization
SectionStartComplete
M- 1 Mantoloking

12/3/12

12/3/12

M - 2 Mantoloking - Normandy

12/4/12

12/4/12

M - 3 Normandy - Chadwick

12/10/12

12/11/12

M - 4  Lavallette

12/12/12

12/12/12

M - 5 Ortley

12/13/12

12/14/12

M - 6 Seaside Heights

12/15/12

12/15/12

M - 7 Seaside Park and South Seaside Park

   12/16/12

12/16/12

NJNG says they will begin with the section between Downer Ave. in Mantoloking and Dune Avenue in Brick tomorrow. For updates and progress on repressurization log on to njng.com.