Repressurization of Barrier Island Begins Monday
New Jersey Natural Gas (NJNG) has released a two-week plan to re-gas sections of the Barrier Island from Mantoloking to South Seaside Park beginning Monday, December 3. The plan is to divide the system into seven sections with crews following behind to rebuild meter sets until all customers who can be serviced again have been. The seven sections have been split as follows:
Pressurization | ||
Section | Start | Complete |
M- 1 Mantoloking | 12/3/12 | 12/3/12 |
M - 2 Mantoloking - Normandy | 12/4/12 | 12/4/12 |
M - 3 Normandy - Chadwick | 12/10/12 | 12/11/12 |
M - 4 Lavallette | 12/12/12 | 12/12/12 |
M - 5 Ortley | 12/13/12 | 12/14/12 |
M - 6 Seaside Heights | 12/15/12 | 12/15/12 |
M - 7 Seaside Park and South Seaside Park | 12/16/12 | 12/16/12 |
NJNG says they will begin with the section between Downer Ave. in Mantoloking and Dune Avenue in Brick tomorrow. For updates and progress on repressurization log on to njng.com.